College of San Mateo Building 14 Modernization

Building 14

Project Description:

The scope of this project includes the renovation of Building 14 for general assignment classrooms. Improvements are expected to include classroom reconfiguration, new finishes in classrooms and corridors, accessibility improvements for restrooms, and enhanced entries and lobbies. Classroom improvements include new furnishings and the installation of smart classroom technology.

Project Benefits:

This project will enable Building 14 to takes its place on the CSM campus as one of the principal general assignment classroom facilities. Its central location makes it ideal of this use. This project will enable Building 14 to compliment Building 16 in meeting that objective. When completed, it is anticipated that it will contribute additional medium sized (50-student capacity) classrooms to the campus. These classrooms will be outfitted with “smart classroom” technology which will keep CSM at the forefront of contemporary learning centers.

Schedule

  • Programming / Design Phase: April 2007 - March 2008
  • Bidding Phase: March 2008- April 2008
  • Construction Phase: June 2008 - November 2008
  • Occupancy: Spring, 2009

Status:

Complete