District Office Restroom Renovation Project

​This project will modernize the District Office restrooms with improved energy efficiency and ventilation, as well as fixture replacements. Drinking fountains with bottle filling stations will be available on each floor. 


October 13th, 2014 - February 12th, 2015

1st Floor Restrooms: October 13, 2014 through December 9, 2014 3rd Floor Restrooms: November 6, 2014 through December 31, 2014 2nd Floor Restrooms: December 24, 2014 through February 12, 2015


The construction schedule has been designed to minimize closure periods as well as disruption to staff. The Contractor will perform the noisiest demolition work during evening hours.
Careful attention to building air quality and general tidiness will remain a focus throughout the project. Dust will be confined to the work area by sealing ducts, installing plastic barriers and sticky mats at the point of entry, and frequent vacuuming.​