Skyline Building 14 Renovation

The project will renovate the Child Development Center play yards displaced by the Parking Lot L project, upgrade path of travel through Building 14 to meet DSA requirements, and replace old windows.

Benefits

The project will improve the play yard experience for children at the Child Development Center, correct deficiencies in the windows, and make the building more easily accessible to students, faculty, staff, and visitors.

Schedule

  • Programming/Design: Through September, 2018
  • DSA Review: October, 2017 – February, 2018
  • Bidding: March 2018 – April 2018
  • Construction: May 2018 – November 2018
  • Completion: November 2018

Status

In Process

Contact Information

Campus Construction Manager

  Glenn Claycomb
  650-378-7338
  claycombg@smccd.edu

Architect / Engineer

  Artik Art & Architecture

General Contractor

  TBD