Districtwide Exterior Lighting Upgrade Project

Contact   Information:

District Energy and   Sustainability Manager
 
Joe Fullerton
  Telephone: 650 358-6848
  E-Mail: fullertonj@smccd.edu

Construction Project   Manager
  Peter Hempel
  Telephone: 650 378-7336
  E-Mail: hempelp@smccd.edu

Design- Build   Entity
Intermountain Electric Company

DW lighting

Project Documents

Schedule:

  • Project Complete January 2018

Description:

This Design- Build Project will upgrade approximately 1,260 exterior fixtures along the pedestrian pathways of Cañada, CSM, and Skyline Campuses.  The controls for the fixtures will be integrated with the existing Building Management System.

Benefits:

The new lighting system will send and receive critical data that will enable the District Facilities staff to better control a more efficient lighting system. This will result in operational and security improvements in addition to long term energy savings.

 

Status:

Project Complete