This project will enable the District to create a home for student Learning Communities (Puente Project, Umoja, Mana, Honors Project and Project Change), most coming from other building locations within the CSM campus. This renovation will create an environment for the students to gather to share ideas and experiences of their education and a place for social interaction in a welcoming environment.



  • Jan.- March 2018: Develop Procurement Contract Documents
  • April-June 2018: Proposal Period
  • July 2018: Board Approval of Contract
  • Aug. 2018- May 2019: Construction
  • June 2019: Occupancy