06 Mar 07 Bridging Documents & RFP Development
n
nDec
2006 2 Pre-Qualification Conferences, > 120 Attendees
n
nFeb
2007 Interview & Short List -- 3 DB Teams
n
nJuly
& Aug 2007 Review Proposals -- 3 DB Teams
n
nSept
2007 Contract Award to DB Team with Best Value Proposal
n
nFall
2007-2008 Design Process
n
n2008
Start Construction
n
n2013
Finish Construction