Facilities Excellence
DW Energy Efficiency
Project Status
Work Completed By the Numbers
Light Fixtures Retrofitted Phase 1 & 2
Canada
4,065
Skyline
668
CSM
4,818
Air Handlers Refurbished
Canada
27
Skyline
32
CSM
54
Heat/Vent Units Refurbished
Canada
26
Skyline
163
CSM
117