Project Update: Preston Pipeline was awarded the contract and started work on site 11/28/04. Substantial rains during December slowed progress. Substantial completion was reached
in January ‘05.
Budget Update:
- Project Budget:
$950,000
- Source of Funds:
Measure C
Schedule Update: On schedule
Scope: Replacement of Hot Water Distribution Loop throughout campus to repair water leaks and
provide for future
connections to Building 6 and 7A.
Delivery Method: Design/Bid/Build
Phase: Construction
Design Team: Sandis Humber Jones
Contractor: Preston Pipelines