Project Update: PG&E relocated a section of gas line around the proposed soccer facility
located to the south of portable
3D. Trenching and backfilling was performed by Bothman Construction at a substantial savings. The new pipe was
installed the week of 12/13/04 and
tied in on 12/21/04. Project was completed on time and under budget.
Budget
Update:
-Project Budget:
$50,000
- Source of
Funds: Measure C
Schedule Update: Complete
Scope: Relocate the PG&E main gas line from under Portable 3D.
Delivery Method: PG&E project
Phase: Design
Design Team: PG&E
Contractor: Trenching – Bothman
Piping – P.G. & E.