Project Update: The Skyline lower soccer field was completed September 8, 2004. The baseball
field is scheduled for
completion in January 2005. The base rock is in place for the tennis courts and
the upper soccer field. Modular
buildings drawings are being reviewed by DSA.
Project Budget:
- Project Budget:
$9.5M
- Source of Funds: Local Funding
Schedule Update: On schedule
Scope: This is a phased
Design/Build project, with design and construction activities proceeding concurrently. Scope includes upgrading football/soccer field to synthetic turf, installing new synthetic turf baseball
field and new synthetic turf soccer field.
Delivery Method: Design/Build
Phase: Complete/Construction
Design Team: Bothman/CMX