Project Update: Coating of the Co-Generation units and Building 2 HV units is scheduled
for spring ‘05 as is
Building 5 HVAC unit structural repair and unit refurbishment. The coating will protect equipment and prolong service life.
Budget Update:
- Project Budget :
$16.9 M
- Source of funds:
Measure C
Schedule Update: Construction targeted to begin in spring ’05
Scope: Energy repair and efficiency upgrade of all major building systems
Delivery Method: Design/Build
Phase: Construction
Design Team: Chevron Energy Solutions