Project Update
Construction
Documents were submitted to DSA for review as targeted on 8/1/04. Project is
targeted to go to bid in April ‘05.
Groundbreaking will occur in summer ’05. Construction completion targeted for the fourth quarter of ‘06.
Budget Update:
- Project Budget:
$27.2M
- Source of funds:
Measure C and State Funds
Schedule Status: On schedule
Scope: New construction of library/learning resource center.
Delivery Method: Design/ Bid/Build
Phase: Design
Design Team: Noll & Tam Architects