Project Update: The Contractor
mobilized on site December 13, 2004. Construction of the temporary access road was started. Demolition of
Fencing has started. Earthwork
will start when the soil is drier.
Budget Update:
- Project Budget: $1,
831, 525
- Source of funds:
Local Funding
Schedule Status: On schedule
Scope: This is a phased
Design/Build project, with design and construction activities proceeding concurrently. Scope includes renovations
to natural turf baseball fields and new synthetic turf soccer field
Delivery Method: Design/Build
Phase: Construction
Design Team: Bothman, CMX