Project Update: Rudolph & Sletten is the contractor. Project successfully bid within budget. Construction commenced in September ’04. Project on-schedule for re-occupancy to occur in January ‘06.
Budget Update:
- Project Budget –
$10.0M
- Source of funds:
Measure C, State Capital Outlay Funding and Local Funds
Schedule Update: On schedule
Scope: Retrofit existing building to comply with ADA requirements and fire/life safety code requirements. Renovate and modernize
fixtures, finishes, building
systems, and equipment.
Delivery Method: Design/Bid Build
Phase: Construction
Design Team: Interactive Resources