Project Update: DSA approval expected mid January ’05. The occupants of the building
will remain where they are
for the Spring semester due to the recent request to explore a new design of
the third floor. Despite
the design changes, this project will bid in late Feb to stay on schedule for
Public Works Board approval
before the 06/30/05 deadline.
Budget Update:
- Project Budget:
$8.3M
- Source of Funds: Measure C, Local Funds and
State Capital Outlay.
Schedule Update: On schedule
Scope: Modernization of Building 8 Language Arts and Business (including Cosmetology and
Auto-tech) Divisions. To include
the addition of Smart Classrooms. This Modernization Project is being combined
with the Building 8 Seismic
Project. The state funded seismic project was previously listed as Project 216.
Delivery Method: Design/Bid/Build
Phase: Design
Design Team: Sugimura and Associates Architects
Contractor: TBD