Project Update: College of San Mateo construction commenced April ‘04. The College of San Mateo Baseball Field is targeted for completion in
February ’05, pending weather. Mondo has been laid on
part of the running track.
DSA review of Modular Buildings and Structural issues is underway. Design of
the Multi Use Events Field design is underway.
Project Budget:
- Project Budget:
$6.5M
- Source of Funds: Local Funding
Schedule Update: On Schedule
Scope: This is a phased Design/Build project, with design and construction activities proceeding concurrently. Scope includes installing
new synthetic turf football field, new Mondo
track surface, new synthetic turf baseball field
and tennis court surfacing
Delivery Method: Design/Build
Phase: Complete/Construction
Design Team: Bothman/CMX