Project Update: DSA approval was received on 12/28/04. Project will be out to bid in
January ’05 with a planned March
’05 contract award.
Budget Update:
- Project Budget: $3.5M excluding FF&E (to
be provided by users)
- Source of funds:
Measure C, Local Funds and Local Law Enforcement Consortium
Schedule Update: On Schedule
Scope: New construction of Regional Public Safety Center.
~9,000 square foot, single story structure housing training facility for local law
enforcement cadets.
Delivery Method: Design/Bid/ Build
Phase: Design
Design Team: DES Architects + Engineers