CAN B1 Gymnasium Hazardous Building Materials Survey

RGA Environmental will conduct a Hazardous Building Materials Survey of the existing Gym Building; taking samples of interior, exterior, roof, and paving materials for lab testing.

SCHEDULE

January 14th, 2016 - January 15th, 2016

CAMPUS IMPACT

No classes or activities are scheduled in the building during this period. Building will be closed for the duration of the sampling. The samples will be taken in every room of the existing Gym Building, from the exterior wall, on the roof, and the site paving materials. The survey will be completed by 1:00PM on January 15