From: Glass, Danny W.
Sent: Wednesday, March 01, 2006 2:28 PM
To: Canada Employees
Cc: Nielsen, Elisabeth
Subject: FW: Canada College Power Shutdown Notice

Please read this message in its entirety.

PROJECT NAME:

 

Caņada Building 9

     

PROJECT DESCRIPTION:

 

Underground utility electrical work.

     

SCHEDULE:

 

Partial Campus Power Outages Scheduled for:

·        Friday Night, March 3, 2006 from 10:30pm till ~ 2am Saturday morning

     

CAMPUS IMPACT:

 

There will be no power or data to the following buildings on the Caņada campus during this time:     Building 13, 16, 17, 18, 19, 20, 21, 22

Before you leave campus prior to these outages, please: 

·               Shut down all office equipment including computers, printers and copiers before you leave your work area (this will help protect equipment from damage).

·               Make alternative arrangements for any organisms that must be sustained which require a regulated temperature and/or cannot survive a change in temperature beyond 6 hours - i.e. any science lab experiments;

·               Remove all perishable items from faculty/staff refrigerators; 

     

PROJECT CONTACT:

 

Please direct any questions or concerns related to this project to:

     

NAME:

 

Peter Hempel

EMAIL:

 

hempelp@smccd.edu

TELEPHONE:

 

(650) 306-3169

     

For more information regarding the Capital Improvement Program, please visit the Campus Construction Update page at:   http://www.smccd.edu/accounts/facilities/planconstruct/NTP_Default_1.html