CSM Building 36 Punchlist

Item # Date Requested Room # Room Name Description of request Requested By Approved   (Y/N) Estimated date of completion Comments
1 2/16/2006   All labs Secure drain screens at epoxy sinks. Use of epoxy is acceptable.   Y Completed 5/25/06  
2 3/7/2006   All labs and lecture rooms At AV cabinet (tot 16): Install Schlage CL1000PB door cabinet locks, 6 pin cylinder, 1" throw, 626 finish, F keyway   Y 9/15/06  
3 3/7/2006   All labs and lecture rooms Verify installation of Timberline locks in millwork. Provide key schedule.   Y    
6 2/16/2006 112, 114, 125 Physics labs Install unistrut at 8' per plans 9' as requested David Locke Y Completed 5/25/06  
7 2/16/2006 112, 114, 125 Physics lab All lamps in room must be operable by room switches David Locke Y Completed 5/25/06  
8 2/16/2006 112, 114, 125 Physics lab Install delayed action closer David Locke Y Completed 5/25/06  
9 2/16/2006 112, 114, 125 Physics lab Provide magnetic sheet for door lite   Y    
10 2/16/2006 112, 114, 125 Physics lab The installed casters in locked position do not adequately prevent table from moving. Provide caster type similar to ones in ES lab, which when locked prevent rolling and swiveling. David Locke Y    
11 2/16/2006 112, 114, 125 Physics lab Provide moveable table heights which align with peninsula table top. Peninsula top heights range from 36" +/- 1/2". Provide level tables. David Locke Y    
12 3/7/2006 112, 114 Physics lab Countertop at teaching station- chamfer bottom edge. Smooth joints between tops. Patch exposed drip edges. David Locke Y    
14 2/16/2006 114 Physics lab Provide ceiling hung curtains David Locke Y Completed 7/28/06  
21 2/16/2006 119 ES lab Provide tackable surface Linda Hand Y Completed 5/25/06  
22 2/16/2006 119 ES lab Change tall cabinet doors from glass to solid Linda Hand Y Completed 5/25/06  
24 2/16/2006 125 Physics Stockroom Modify solid back for stockroom shelving David Locke Y Completed 5/25/06  
25 3/7/2006 125 Physics Stockroom Non-AV casework within room should be keyed alike. Change TC103 locks to TC104.   Y    
26 3/7/2006 127 Optics Lab Relocate ceiling hung unistrut such that projector screen is not obstructed. Jim Petromilli Y Completed 7/28/06  
28 2/16/2006 127 Optics Lab Provide laser curtains David Locke Y Completed 7/28/06  
32 2/16/2006 200 Botany lab Install (2) backpack hooks per station Tania Beliz Y Completed 5/25/06  
34 2/16/2006 204 Microbiology Install backpack hooks Kim Meyer Y Completed 5/25/06  
35 2/16/2006 204 Microbiology Complete gas turret installation Kim Meyer Y Completed 5/25/06  
36 2/16/2006 206C Culture Prep Provide aesthetically acceptable routing of copper piping and power supply to BSC Kim Meyer Y 8/18/06 Added scope- change from vacuum to gas
37 2/16/2006 206C Culture Prep Provide duplex receptacle at countertop   Y Completed 8/4/06  
38 2/16/2006 217A Anatomy Prep Install bumpers and FRP   Y Completed 5/25/06  
39 2/16/2006 223 Zoology lab Install (2) backpack hooks per station Michael Bucher Y Completed 5/25/06  
40 3/7/2006 300 Organic Chem lab Install filler panels to conceal plumbing behind acid/ flammable cabinets   Y Completed 5/25/06  
42 2/16/2006 300 Organic Chem lab Install mobile instructor's desk Yin Mei Lawrence Y Completed 5/25/06  
43 2/16/2006 306, 321, 329 Chem lab Install backpack hooks Kate Deline Y Completed 5/25/06  
44 3/7/2006 319 Lecture  Verify overhang at teaching station. Does not appear to have been extended.   Y Completed 5/25/06  
47 2/24/2006 400 Observatory Correct water damaged deck coating Darryl Stanford Y Completed 5/25/06  
48 2/24/2006 400 Observatory Complete hardware installation Darryl Stanford Y Completed 5/25/06  
49 2/24/2006 400 Observatory Cabinet doors to not open wide enough to allow shelves to be pulled straight out. Darryl Stanford Y    
50 2/24/2006 400A Observatory Install data and power abv countertop Darryl Stanford Y Completed 5/25/06  
52 6/30/2006   labs Corrections to operation of casework- locks and catches, missing/ loose pulls, missing label holders   Y Completed 7/28/06  
53 7/2/2006 101, 301 staff restrm  Correct function of locks to prevent accidental interruptions David Locke Y Completed 8/9/06  
54 7/2/2006   All corridor doors Adjust doors/ air pressure so that doors close properly   Y Completed 8/14/06