CSM Building 36 Punchlist
| Item # | Date Requested | Room # | Room Name | Description of request | Requested By | Approved (Y/N) | Estimated date of completion | Comments |
| 1 | 2/16/2006 | All labs | Secure drain screens at epoxy sinks. Use of epoxy is acceptable. | Y | Completed 5/25/06 | |||
| 2 | 3/7/2006 | All labs and lecture rooms | At AV cabinet (tot 16): Install Schlage CL1000PB door cabinet locks, 6 pin cylinder, 1" throw, 626 finish, F keyway | Y | 9/15/06 | |||
| 3 | 3/7/2006 | All labs and lecture rooms | Verify installation of Timberline locks in millwork. Provide key schedule. | Y | ||||
| 6 | 2/16/2006 | 112, 114, 125 | Physics labs |
Install unistrut at |
David Locke | Y | Completed 5/25/06 | |
| 7 | 2/16/2006 | 112, 114, 125 | Physics lab | All lamps in room must be operable by room switches | David Locke | Y | Completed 5/25/06 | |
| 8 | 2/16/2006 | 112, 114, 125 | Physics lab | Install delayed action closer | David Locke | Y | Completed 5/25/06 | |
| 9 | 2/16/2006 | 112, 114, 125 | Physics lab | Provide magnetic sheet for door lite | Y | |||
| 10 | 2/16/2006 | 112, 114, 125 | Physics lab | The installed casters in locked position do not adequately prevent table from moving. Provide caster type similar to ones in ES lab, which when locked prevent rolling and swiveling. | David Locke | Y | ||
| 11 | 2/16/2006 | 112, 114, 125 | Physics lab | Provide moveable table heights which align with peninsula table top. Peninsula top heights range from 36" +/- 1/2". Provide level tables. | David Locke | Y | ||
| 12 | 3/7/2006 | 112, 114 | Physics lab | Countertop at teaching station- chamfer bottom edge. Smooth joints between tops. Patch exposed drip edges. | David Locke | Y | ||
| 14 | 2/16/2006 | 114 | Physics lab | Provide ceiling hung curtains | David Locke | Y | Completed 7/28/06 | |
| 21 | 2/16/2006 | 119 | ES lab | Provide tackable surface | Linda Hand | Y | Completed 5/25/06 | |
| 22 | 2/16/2006 | 119 | ES lab | Change tall cabinet doors from glass to solid | Linda Hand | Y | Completed 5/25/06 | |
| 24 | 2/16/2006 | 125 | Physics Stockroom | Modify solid back for stockroom shelving | David Locke | Y | Completed 5/25/06 | |
| 25 | 3/7/2006 | 125 | Physics Stockroom | Non-AV casework within room should be keyed alike. Change TC103 locks to TC104. | Y | |||
| 26 | 3/7/2006 | 127 | Optics Lab | Relocate ceiling hung unistrut such that projector screen is not obstructed. | Jim Petromilli | Y | Completed 7/28/06 | |
| 28 | 2/16/2006 | 127 | Optics Lab | Provide laser curtains | David Locke | Y | Completed 7/28/06 | |
| 32 | 2/16/2006 | 200 | Botany lab | Install (2) backpack hooks per station | Tania Beliz | Y | Completed 5/25/06 | |
| 34 | 2/16/2006 | 204 | Microbiology | Install backpack hooks | Kim Meyer | Y | Completed 5/25/06 | |
| 35 | 2/16/2006 | 204 | Microbiology | Complete gas turret installation | Kim Meyer | Y | Completed 5/25/06 | |
| 36 | 2/16/2006 | 206C | Culture Prep | Provide aesthetically acceptable routing of copper piping and power supply to BSC | Kim Meyer | Y | 8/18/06 | Added scope- change from vacuum to gas |
| 37 | 2/16/2006 | 206C | Culture Prep | Provide duplex receptacle at countertop | Y | Completed 8/4/06 | ||
| 38 | 2/16/2006 | 217A | Anatomy Prep | Install bumpers and FRP | Y | Completed 5/25/06 | ||
| 39 | 2/16/2006 | 223 | Zoology lab | Install (2) backpack hooks per station | Michael Bucher | Y | Completed 5/25/06 | |
| 40 | 3/7/2006 | 300 | Organic Chem lab | Install filler panels to conceal plumbing behind acid/ flammable cabinets | Y | Completed 5/25/06 | ||
| 42 | 2/16/2006 | 300 | Organic Chem lab | Install mobile instructor's desk | Yin Mei Lawrence | Y | Completed 5/25/06 | |
| 43 | 2/16/2006 | 306, 321, 329 | Chem lab | Install backpack hooks | Kate Deline | Y | Completed 5/25/06 | |
| 44 | 3/7/2006 | 319 | Lecture | Verify overhang at teaching station. Does not appear to have been extended. | Y | Completed 5/25/06 | ||
| 47 | 2/24/2006 | 400 | Observatory | Correct water damaged deck coating | Darryl Stanford | Y | Completed 5/25/06 | |
| 48 | 2/24/2006 | 400 | Observatory | Complete hardware installation | Darryl Stanford | Y | Completed 5/25/06 | |
| 49 | 2/24/2006 | 400 | Observatory | Cabinet doors to not open wide enough to allow shelves to be pulled straight out. | Darryl Stanford | Y | ||
| 50 | 2/24/2006 | 400A | Observatory | Install data and power abv countertop | Darryl Stanford | Y | Completed 5/25/06 | |
| 52 | 6/30/2006 | labs | Corrections to operation of casework- locks and catches, missing/ loose pulls, missing label holders | Y | Completed 7/28/06 | |||
| 53 | 7/2/2006 | 101, 301 | staff restrm | Correct function of locks to prevent accidental interruptions | David Locke | Y | Completed 8/9/06 | |
| 54 | 7/2/2006 | All corridor doors | Adjust doors/ air pressure so that doors close properly | Y | Completed 8/14/06 |