Schedule:
- Design Phase: September 2006 – October 2007
- Bidding Phase: October 2007 – November 2007
- Construction Phase: February 2008 – February 2009
- End of Project: February 2009
Funding Source(s):Measure A and State Funding
Business Opportunities

Description:
The scope of work for this project is to build a new facilities maintenance center at the Canada College Campus.
Benefits:
This project will allow Facilities to be better equipped to address maintenance issues as well as emergency repairs to the campus. It will also allow for the expansion of physical education classes and equipment in B1 where they are currently housed.
Status: About to begin construction in the field.
|