PROJECT NAME:
Building # 5/6 McCarthy Projects
PROJECT DESCRIPTION:
Parking Lot #3 C Space Striping/painting
SCHEDULE:
5/17/08 - Saturday
CAMPUS IMPACT:
Parking Lot 3C will be closed to traffic and pedestrians. Sections A and B will remain open but construction equipment will also be temporarily located in the area.
PROJECT CONTACT:
Please direct any questions or concerns related to this project to:
NAME:
Mark Eppard, Project Manager
EMAIL:
eppardm@smccd.edu
TELEPHONE:
650-378-7336
For more information regarding the Capital Improvement Program, please visit the Campus Construction Update page at: http://www.smccd.net/accounts/facilities/planconstruct/default.html
Diane Martinez Facilities Operations Manager College of San Mateo (650) 574-6577 (650) 574-6203
Facilities Planning & Operations Phone: (650) 574-6512 Fax: (650) 574-6574
Construction Planning Department Phone: (650) 358-6785 Fax: (650) 358-6764