PROJECT NAME:

 

Traffic Study

 

 

 

PROJECT DESCRIPTION:

 

Installation of traffic count monitoring equipment

Traffic count data at the campus entries and important intersections will allow us to make better informed decisions related to capital improvements in those areas.  The monitoring equipment will appear on the roadway as rubber tubing that can be driven over.  Captured data over this 6-week monitoring period will include number of vehicles crossing and date/time information.

 

 

 

SCHEDULE:

 

August 14 – September 22, 2006

 

 

 

CAMPUS IMPACT:

 

none

 

 

 

PROJECT CONTACT:

 

Please direct any questions or concerns related to this project to:

 

 

 

NAME:

 

Linda da Silva

EMAIL:

 

dasilva@smccd.edu

TELEPHONE:

 

650-358-6726

 

 

 