From: Inokuchi, Richard
Sent: Tuesday, November 08, 2005 11:00 AM
To: Skyline Employees; Skyline View; Skyline ASSC
Cc: Da Silva, Linda L.; Nunez, Jose; Powell, Karen; Calibo, Arlene; Miller, Alan; Nielsen, Elisabeth; Moezzi, Saaid
Subject: Construction Notice - Roofing Work on Building 1

                                         

Hi everyone – before we get too far into the rainy season – we are going to attempt to get the roofing work on Building 1 completed.  To that end, work will again begin tomorrow, Wednesday, November 9 and last until December 17.

This will mean –

  1. [November 9 thru November 21]  A debris box will have to be spotted close to the Co-Generation unit by the ceramics loading dock.
  2. [November 9 and 10]  Sections of the sidewalks and walkways along the south side (Lot 1 side) of Building 1will be closed during short periods.
  3. [November 9 thru November 21]  The concrete deck area off the 3rd floor (by Administration) will be closed during short periods.
  4. [November 9 thru December 17]  The roof pathway from Auto leading up to the 3rd floor of Building 1 will be closed.
  5. [November 27 thru December 17]  A debris box will have to be spotted at the southwest corner of Building 1 (on the road entrance to Auto).

Building 1 entrance ways will remain open throughout the duration of this project, to include the pedestrian and vehicular pathways between Building 1 and Building 8.  All of the roof demolition work is scheduled from 10:00 pm to 7:00 am. in efforts to minimize the disruption to campus activities.      

3rd Floor Building 1 users and occupants are requested to keep their windows closed, especially in Rooms 1304 and 1306, as much as possible during these roofing activities.

Our Swinerton Team will be posting notices and interior and exterior signs to inform everyone, and to control and direct pedestrian and vehicular traffic.  Sajid Sulaiman is our Swinerton Team project lead and he can be reached at ext 7022 or sulaimans@smccd.net if you have questions or concerns.

I apologize for this inconvenience and appreciate your patience.  I want to also thank those of you who attended yesterday’s Student Support and Community Services Center (Building 6) “Topping Off” Ceremony – a true landmark event for our college.  If you want to look at a real-time view of the construction of our new Building 6 (Student Support and Community Services Center), please click on - 

http://www.smccd.net/accounts/smccd/webcams/skystudentcenter.asp   Stay tuned for further news of a similar ceremony for our Science Annex (Building 7A).

To review our Capital Improvement Program on our District web site, please click on - http://www.smccd.net/accounts/facilities/planconstruct/SKY_Projects_Summary_06.30.04.pdf

You can also access this web site through our Skyline Home Page  http://skylinecollege.net/  by clicking on ‘Campus Construction updates and parking.’

If you’re just interested in past ‘Construction Notices,’ please click on http://www.smccd.net/accounts/facilities/planconstruct/SKY%20Notices.htm#Campus_Construction_Notices

Please be careful around Building 1 and all our other construction areas.  Thanks.