From: Glass, Danny W.
Sent: Friday, September 02, 2005 9:49 AM
To: Canada Employees
Cc: Nielsen, Elisabeth
Subject: Canada Construction Notice

PROJECT NAME:

 

Building 9

     

PROJECT DESCRIPTION:

 

Build small temporary staircase at B18 southeast in order to reroute path of travel through B18, 2nd floor during B9 construction.

     

SCHEDULE:

 

9/7/05 – 9/12/05

     

CAMPUS IMPACT:

 

Minor – existing path of travel will remain operational during staircase construction.

     

PROJECT CONTACT:

 

Please direct any questions or concerns related to this project to:

     

NAME:

 

Anne E. Daley

EMAIL:

 

daleya@smccd.net

TELEPHONE:

 

650.306.3477

     

For more information regarding the Capital Improvement Program, please visit the Campus Construction Update page at:  

http://www.smccd.net/accounts/facilities/planconstruct/CAN_Projects_Summary_Main.htm