FALL SEMESTER START
CONSTRUCTION UPDATE
Completed over Summer 2005
☺ Successful swing of offices and classrooms in Bldg 8 to Pacific Heights, Bldg 1, Bldg 2, and Bldg 5
☺ Successful swing of Cosmetology to Pacific Heights
☺ Summer “Facelift” in Bldg 1
o Rooms = 1105, 1107, 1111, 1115, 1124, 1303, 1304, 1306, 1319 and 1320
o New floor tile in hallways; stairways and restrooms also painted
☺ Concrete foundations poured for Bldgs 6 & 7A
☺ Bldg 8 hazardous materials removed; demolition getting underway
☺ New floor in Portable 3B
☺ Athletic Fields
o Outdoor restroom near completion
o Tennis courts opened
o Upper soccer field opened
o Started Parking Lot 11 (north of track) construction
Capital Improvement Program
1. Pacific Heights
o Ongoing - District meetings & discussions continue regarding future construction plans for the Pacific Heights area – i.e. site for future Cosmetology building and Child Development Center building
o Use as a Swing Space
§ August 2004 to May 2006 - Swing space for Bldg 3
§ June 2005 to December 2006 - Swing space for Bldg 8
§ June 2005 to January 2012 - Swing space for Cosmetology
§ December 2006 to June 2008 - Swing space for some of Bldg 7, Facilities warehouses, all Swinerton
o Ongoing - construct Cosmo dispensary area and ADA compliant unisex restroom near south entrance
2. Bldg 1 ‘Summer 2005 Facelift’
o Summer 2005 - exact dates of all work TBD
o 11 rooms identified - scope of work in each room varies - paint, floor tile, ceiling, furniture, window treatments, SMART technology
§ Ongoing - finishing furniture installation
§ Early September - start window treatment installation
3. Bldg 3 Seismic Retrofit and Modernization
o August 15 - parking in Staff Lot 3 opened
o March 2006 - Complete construction
o May 2006 (end Spring 2006) – PE Department faculty/staff/classes move back to Bldg 3
4. Bldg 8 Seismic Retrofit and Modernization
o End June - Bldg 8 closed
o Ongoing - Modular restroom in front of Bldg 7 being install
o December 2006 (end Fall 2006) – Bldg 8 faculty/staff/classes move from swing locations back to Bldg 8
5. Fall 2005 “One Off” Projects - exact dates for most TBD
o October - Paint exterior of Portables 3A, 3B, 3C, 3D, and 3E
o October - Construct ADA/pedestrian walkway behind Bldg 5 from Staff Lot 6 to Bookstore
o October - Repair road drain at Marisol T-intersection entrance to campus
o October - Repair and replace pavement along Loop Road between Lot 4 and Track
o October - Install road drainage north of Lot 5 at Pacific Heights Blvd dead end
o Repair and replace pavement at Marisol T-intersection entrance to campus
o Replace ramps at Portables 3A, 3B, 3C, 3D, 3E, and Child Development Center
6. 2005 HVAC Projects - exact dates TBD
o Bldg 1 - replace rooftop HVAC exhaust fans (x7)
§ No exhaust fan air circulation; crane work involved in Staff Lot 1
o Bldg 2 - paint and coat rooftop HVAC unit and rooftop ductwork
§ Periods when HVAC units will need to be shut down
o Co-Generation Unit (outside Bldg 2 loading dock) - paint and coat
§ Periods when Co-Gen unit will need to be shut down
o Bldg 5 - replace rooftop HVAC units (x4)
§ October 1 – Saturday morning Units 1 & 2 shut down; crane work involved
§ October 15 – second Saturday morning Units 3 & 4 shut down; crane work involved
7. Bldg 6 (Student Support & Community Services Center) & Bldg 7A (Science Wing)
o September 2006 (Fall 2006) - Complete construction
o January 2007 (Spring 2007) - Bldg 6 and Bldg 7A “Ribbon Cutting” Opening
8. Building 4 (Bookstore)
o December 2006 (end of Fall 2006) - Bookstore moves to Bldg 6
o April 2007 – Bldg 4 demolished and area landscaped
9. Building 2 (Phase III) – 3rd Floor
o December 2006 (end of Fall 2006) - Cafeteria moves to Bldg 6
o December 2006 (end of Fall 2006) - Student Activities moves to Bldg 6
o June 2007 (end of Spring 2007) - Remaining Bldg 2-3rd Floor faculty/staff/classes move to swing locations (Pacific Heights or other campus locations)
o June 2008 (end of Spring 2008) - Bldg 2-3rd Floor construction complete
10. Building 7 (Allied Health)
o December 2006 (end of Fall 2006) - Bldg 7 faculty/staff/classes move to swing locations
(Bldg 7A or Pacific Heights)
o January 2007 – Bldg 7 closed
o June 2008 (end of Spring 2008) - Bldg 7 faculty/staff/classes move from swing locations back to Bldg 7
11. Facilities Maintenance Center (FMC)
o December 2006 (end of Fall 2006) - Swinerton and Facilities warehouse moves to Pacific Heights
o January 2007 - Start construction
o March 2008 – Facilities warehouse moves back to new Bldg 12; Swinerton remains at Pacific Heights
Athletic Field Improvements Program
12. Track and Lower Soccer Field
o Underground water issues being addressed; redesign of stairs and disabled person ramp that connect lower and upper fields may be needed
o Construction on hold - completion date unknown
13. Upper Soccer Field
o Construction fully complete to include scoreboard install and bleacher assembly
14. Baseball Field
o Mid November - Fully complete construction
15. Tennis Courts
o Mid September - Fully complete construction to include bench install
16. Outdoor Restroom Facility
o Mid September - Fully complete construction
17. New Parking Lot 11 (north of Track)
o 100 parking spaces + 10 disabled person spaces; directly north of track & east of grass soccer field
o End September - Fully complete construction
Our Swinerton Team Doug Henry (Team Chief) 738-7047 / 7041 henryd@smccd.net “One Off” Projects - Athletic Fields - HVAC Projects Zak Conway 738-7042 conwayz@smccd.net Bldg 1 “Facelift” Sajid Sulaiman 738-7022 suilaimans@smccd.net Pacific Heights – Bernard Rottner 738-7037 rottnerb@smccd.net Bldg 3 – Marcus Gary 738-7044 garym@smccd.net Victor Livingston 738-7046 livingstonv@smccd.net Bldg 8 – Marcus Gary Victor Livingston Bldg 6 and 7A – Doug Henry