PROJECT NAME:

 

Canada Zone Control Project

     

PROJECT DESCRIPTION:

 

Asbestos Abatement of Flooring

     
     
     

SCHEDULE:

 

Saturday, July 2, 2005 – Sunday, July 3, 2005

   

Prep Work only will be performed on Friday, July 1, 2005.

     

CAMPUS IMPACT:

 

An asbestos abatement contractor will be removing asbestos flooring in the following locations in Building 8:

Rooms 208, 209, 210, 211, 213, and 214.

Building 13:  Room 121  and Building 3:  Room 225.

     
     

PROJECT CONTACT:

 

Please direct any questions or concerns related to this project to:

     

NAME:

 

Linda Rizzoli – Project Manager

EMAIL:

 

rizzolil@smccd.net

TELEPHONE:

 

650-306-3169

     

For more information regarding the Capital Improvement Program, please visit the Campus Construction Update page at:   http://www.smccd.net/accounts/facilities/planconstruct/NTP_Default_1.html

Note:  Work will be performed by a qualified contractor, Sterling Environmental Services, who is certified by the California Occupational Safety and Health Administration (CAL-OSHA) in the safe containment and removal of asbestos-containing materials.  All work areas will be sealed off and monitored.  An independent certified asbestos inspector, hired by the District, will monitor the entire work process, to oversee and insure the safety and health regulations and codes are followed, and to test and certify that the air is free and clear.