CSM Building 36 Report of Additional Scope Requests
as of August 18, 2006
This report lists the items, identified by faculty and staff, which need additional attention. These items were not in the design-builder’s contract, so they are tracked as additional scope requests. A separate listing of contract items needing remediation is available at http://www.smccd.edu/accounts/facilities/maintoperation/CSMB36Punchlist.htm.
This report provides transparency in the process of vetting and implementing additional scope requests. This report includes items reported initially to Swinerton Management & Consulting, as well as items submitted to the Facilities HelpCenter. When an additional scope request is received, it is reviewed for constructability, cost and relative benefit to the Science curriculum. Priority levels are assigned based on these criteria, from 1 (high priority) on down.
Items are listed in order of status:
· Approved: these items have been approved, funding has been identified, and an estimated date of completion is shown.
· Pending: these are items for which solutions have yet to be identified, or the identified solutions have been targeted for implementation at a future date.
· Not Approved: requestors have withdrawn their requests, approval of other requests have voided the necessity of implementing these requests, or the priority level does not warrant the expense associated with a particular request.
If you have identified an additional scope request and do not see it on this list, please submit the request to the Facilities HelpCenter (look for the link on the left navigation bar). Requests received prior to September 22, 2006 will be considered. As additional scope requests are received, this report will be updated periodically.
|
Item # |
Date Requested |
Room # |
Room Name |
Description of request |
Requested by |
Approved |
Estimated Date of Completion |
Comments |
Priority |
|
101 |
2/22/2006 |
109, 207 |
Lecture |
Instructor at desk blocks projector screen. Extend top by 2' maintaining overhangs; extend chase along back but provide kneespace on front and side |
Jim Petromilli |
Y |
8/25/06 |
|
1 |
|
102 |
2/22/2006 |
215 |
Lecture |
Instructor at desk blocks projector screen. Relocate screen and projector 6' towards window |
Jim Petromilli |
Y |
Completed 8/4/06 |
|
1 |
|
102a |
2/22/2006 |
319 |
Lecture |
Instructor at desk blocks projector screen. Relocate screen and projector 2' towards window; locate projector in front of light fixture (towards front of rm). Extend top by 2' away from window (and sink) maintaining overhangs; add 2' cabinet w/o drawer |
Jim Petromilli |
Y |
8/25/06 |
Projector, screen have been relocated. Pending desk extension |
1 |
|
106 |
2/16/2006 |
112, 114, 125, 109 |
Physics lab + 1st fl lecture |
Change whiteboard to chalkboard (24'x4' per rm) |
David Locke |
Y |
9/1/06 |
|
1 |
|
109a |
2/16/2006 |
112, 114, 125 |
Physics lab |
Exposed plywood backing- 1/4" sheetrock, tape, paint (6 locations total) |
David Locke |
Y |
Completed 8/3/06 |
|
1 |
|
110 |
2/16/2006 |
119 |
ES lab |
Provide (2) additional panels of sliding horizontal whiteboards. |
Linda Hand |
Y |
9/30/06 |
|
1 |
|
110a |
2/16/2006 |
119 |
ES lab |
Remove 1 panel vert sliders from each bay, total 3 |
Linda Hand |
N |
X |
Request withdrawn 8/11 |
1 |
|
116 |
2/16/2006 |
200, 223 |
Botany lab, zoology |
Provide stop at end of the one student table adjacent to AV cabinet |
Kim Meyer |
Y |
9/15/06 |
|
1 |
|
118a |
2/16/2006 |
200A |
Botany Prep |
Provide 72" x 30" metal frame table w/ epoxy top |
Tania Beliz |
Y |
9/1/06 |
|
1 |
|
|
|
|
|
|
|
N |
X |
Done- per contract |
|
|
109 |
2/16/2006 |
112, 114, 125 |
Physics lab |
Exposed plywood backing- wrap with fabric (6 locations total) |
David Locke |
N |
X |
Select drywall option. See Item 109A |
2 |
|
119 |
2/16/2006 |
200A |
Botany Prep |
Provide 8 duplex GFI outlets |
Tania Beliz |
Y |
Completed 7/28/06 |
|
1 |
|
120 |
2/16/2006 |
204 |
Microbiology |
Provide supply of screens for cup sinks. Include 100 shelf clips |
Kim Meyer |
Y |
9/15/06 |
|
1 |
|
122 |
2/16/2006 |
206 |
Bio Stockroom |
Provide shallower counter; 24" similar to Chem stockroom |
Kim Meyer |
Y |
Completed |
|
1 |
|
123 |
2/16/2006 |
206C |
Culture Prep |
Add duplex in southwest corner of room for mini fridge and incubator |
Kim Meyer |
Y |
Completed 7/28/06 |
|
1 |
|
|
|
|
|
|
|
N |
|
|
|
|
124 |
2/16/2006 |
217 |
Anatomy Lab |
Change knob type fixture handles to lever type at one sink. |
Theresa Martin |
Y |
9/15/06 |
|
1 |
|
|
|
|
|
|
|
N |
|
Punchlist item |
|
|
126 |
2/16/2006 |
223 |
Zoology lab |
Install locks at drawers and base cabinets throughout except along window |
Kim Meyer |
N |
X |
See Item 136 |
1 |
|
127 |
2/16/2006 |
306, 321, 329 |
Chem lab |
Add water, sink, gas to instructors bench |
Kate Deline |
Y |
9/8/06 |
|
1 |
|
130 |
3/22/2006 |
105, 205, 305 |
Open offices |
Replace open office 3'x4' whiteboards with 8'w x 4' |
Mike Claire |
Y |
9/30/06 |
|
1 |
|
133 |
5/11/2006 |
|
hallways |
Install (8) 4'w x 3'h lockable solution key display cases in hallways (5)- 1st fl, (3)- 3rd fl |
Barbara Uchida, Linda Hand, Kate Deline |
Y |
9/30/06 |
|
1 |
|
134 |
5/11/2006 |
309 |
|
Millwork, power, data associated w/ copier |
Vic Krimsley |
Y |
Completed 7/28/2006 |
|
1 |
|
135 |
6/19/2006 |
206A |
Media prep |
Add (1) gas turret |
Kim Meyer |
Y |
Completed 8/11/06 |
|
1 |
|
136 |
6/20/2006 |
223 |
Zoology lab |
Install locks at drawers and base cabinets throughout room |
Kim Meyer |
Y |
9/30/06 |
|
1 |
|
137 |
6/20/2006 |
223 |
Zoology lab |
Change doors on upper pair of tall cabinets from solid wood to glass |
Kim Meyer |
Y |
9/30/06 |
|
1 |
|
138 |
6/20/2006 |
204 |
Microbiology |
Remove recessed fire extinguisher cabinet to allow for refrigerator; relocate fire extinguisher |
Kim Meyer |
Y |
8/25/06 |
Pending paint |
1 |
|
139 |
6/20/2006 |
206A, 218 |
Bio Stockroom |
Add pegboard over two sinks (1/rm) |
Kim Meyer |
Y |
9/30/06 |
|
1 |
|
141a |
6/20/2006 |
302 |
O chem lab |
Add 1 ice machine- undercounter (opg 35.5wx30.25h x 29"d); crushed ice |
Vic Krimsley |
Y |
|
|
1 |
|
141b |
6/20/2006 |
306 |
Chem lab |
Add 1 ice machine |
Vic Krimsley |
Y |
|
|
1 |
|
142 |
6/20/2006 |
123 |
Physics Stockroom |
Provide 4 extra shelves total for 48" cabinet |
David Locke |
Y |
9/30/06 |
|
1 |
|
143 |
7/7/2006 |
|
lecture and labs |
Provide 1 extra shelf for each AV cabinet; total 16 |
Jim Petromilli |
Y |
9/30/06 |
|
1 |
|
144 |
7/7/2006 |
300 |
O-chem lab |